Chào anh/chị, em là Phong hiên em đang học về costing, có bài này em ko làm được mong các anh các chị trên diễn đàn giúp đỡ. Em chân thành cảm ơn !
Email: nguyenphong.tfac@gmail.com
Skype: nguyenphong.tfac
Phone: 01689905744
SM makes two products, Z1 and Z2. Its machines can only work on one product at a time. The two products are worked on in 2 departments by differing grades of labour. The labour requirements for the two products are as follows:
Minutes per unit of product
Z1 Z2
Department 1 12 16
Department 2` 20 30
There is currently a shortage of labour and the maximum times available each day in Departments 1 and 2 are 480 and 840 minutes, respectively
The current selling prices and cost for the two products are shown below:
Z1 Z2
$ Per unit $ per unit
Selling price 50 65
Direct materials 10 15
Direct labour 10.4 6.2
Variable overheads 6.4 9.2
Fixed overheads 12.8 18.4
Profit per unit 10.4 16.2
As part of budget-setting process, SM needs to know the optimum output
levels. All output is sold
Requirements
Using contribution analysis, calculate the ‘ Profit-maximising’ output each
day, and the contribution at this level of output.
Email: nguyenphong.tfac@gmail.com
Skype: nguyenphong.tfac
Phone: 01689905744
SM makes two products, Z1 and Z2. Its machines can only work on one product at a time. The two products are worked on in 2 departments by differing grades of labour. The labour requirements for the two products are as follows:
Minutes per unit of product
Z1 Z2
Department 1 12 16
Department 2` 20 30
There is currently a shortage of labour and the maximum times available each day in Departments 1 and 2 are 480 and 840 minutes, respectively
The current selling prices and cost for the two products are shown below:
Z1 Z2
$ Per unit $ per unit
Selling price 50 65
Direct materials 10 15
Direct labour 10.4 6.2
Variable overheads 6.4 9.2
Fixed overheads 12.8 18.4
Profit per unit 10.4 16.2
As part of budget-setting process, SM needs to know the optimum output
levels. All output is sold
Requirements
Using contribution analysis, calculate the ‘ Profit-maximising’ output each
day, and the contribution at this level of output.